Response: Devon County Historic Environment Team
12/10/2026 From Stephen Reed, Principal Historic Environment Officer Devon County Historic Environment Team to Miss C Roissetter, Devon County Council
What It States
Archaeological Potential: The western extension of the site is an undisturbed greenfield area with high potential to contain prehistoric and Romano-British iron production deposits.
Risk of Destruction: Proposed groundworks risk exposing and permanently destroying archaeological and artefactual deposits associated with a nearby prehistoric enclosure identified via LiDAR data in 2011.
Staged Work Program: The required mitigation is envisioned as a staged programme of archaeological works, beginning with the excavation of trial trenches to check for heritage assets.
Policy Basis: The recommended protections are based on Policy DM07 of the North Devon and Torridge Local Plan and Policy HE10 of the National Planning Policy Framework (2026).
What It Asks For
Written Scheme of Investigation: The application should ideally be supported by a pre-determination Written Scheme of Investigation (WSI) detailing a programme of archaeological mitigation.
Pre-Commencement Condition: If a WSI is not submitted prior to determination, a strict pre-commencement condition must be attached to the planning permission blocking all development until a WSI is formally approved in writing by the Local Planning Authority.
Post-Excavation Condition: A follow-up condition is requested to prevent the development from being brought into use until post-investigation assessments, analysis, publication, and archiving are fully completed and approved.
Reporting and Archiving: The results of the fieldwork must be compiled into a detailed, illustrated report, and all physical finds must be formally deposited according to national and local guidelines.
Response Comments from Stephen Reed, Principal Historic Environment Officer Devon County Historic Environment Team ref: ARCH/DM/ND/43463b I refer to your recent re-consultation, the Historic Environment Team has no additional comments to make to those previously made, namely: The proposed development lies to the north and downslope from a possible prehistoric enclosure, identified from LiDAR data in 2011, and within a landscape where findspots of prehistoric flint artefacts are recorded in the county Historic Environment Record. In addition, archaeological work in the vicinity of Brayford has identified evidence associated with the Romano-British iron production industry that operated in this landscape. While the eastern part of the application area has been disturbed by the construction of the extant poultry buildings the western extension of the development site is a greenfield undeveloped site. As such, groundworks in the western part of the application area for the construction of the proposed development have the potential to expose and destroy archaeological and artefactual deposits associated with the above-mentioned heritage assets. The Historic Environment Team would therefore advise that any impact of development upon the archaeological resource here should be mitigated by a programme of archaeological work that should investigate, record and analyse the archaeological evidence that will otherwise be destroyed by the proposed development. The Historic Environment Team recommends that this application should be supported by the submission of a Written Scheme of Investigation (WSI) setting out a programme of archaeological work to be undertaken in mitigation for the loss of heritage assets with archaeological interest. The WSI should be based on national standards and guidance and be approved by the Historic Environment Team. If a Written Scheme of Investigation is not submitted prior to determination the Historic Environment Team would advise, for the above reasons and in accordance with Policy DM07 of the North Devon and Torridge Local Plan 2011 - 2031 and Policy HE10 of the National Planning Policy Framework (2026), that any consent your Authority may be minded to issue should carry the condition as worded below, based on model Condition 55 as set out in Appendix A of Circular 11/95, whereby: ?No development shall take place until the developer has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation (WSI) which has been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out at all times in accordance with the approved scheme as agreed in writing by the Local Planning Authority.? Reason 'To ensure, in accordance with Policy DM07 of the North Devon and Torridge Local Plan 2011 - 2031 and Policy HE10 of the National Planning Policy Framework (2026), that an appropriate record is made of archaeological evidence that may be affected by the development.' This pre-commencement condition is required to ensure that the archaeological works are agreed and implemented prior to any disturbance of archaeological deposits by the commencement of preparatory and/or construction works. In addition, the Historic Environment Team would advise that the following condition is applied to ensure that the required post-excavation works are undertaken and completed to an agreed timeframe, whereby: ?The development shall not be brought into its intended use until (i) the post investigation assessment has been completed in accordance with the approved Written Scheme of Investigation and (ii) that the provision made for analysis, publication and dissemination of results, and archive deposition, has been confirmed in writing to, and approved by, the Local Planning Authority.? Reason ?To comply with Policy HE10 of the National Planning Policy Framework (2026), which requires the developer to record and advance understanding of the significance of heritage assets, and to ensure that the information gathered becomes publicly accessible.? I would envisage the programme of archaeological work as taking the form of a staged programme of archaeological works, commencing with the excavation of a series of trial trenches to determine the presence and significance of any heritage assets with archaeological interest that will be affected by the development. Based on the results of this initial stage of works the requirement and scope of any further archaeological mitigation can be determined and implemented either in advance of or during construction works. This archaeological mitigation work may take the form of full area excavation of all or targeted part(s) of the development site in advance of construction works commencing. The results of the fieldwork and any post-excavation analysis undertaken would need to be presented in an appropriately detailed and illustrated report, and the finds and archive deposited in accordance with relevant national and local guidelines. I will be happy to discuss this further with you, the applicant or their agent. The Historic Environment Team can also provide the applicant with advice on the scope of the works required, as well as contact details for archaeological contractors who would be able to undertake this work. Provision of detailed advice to non-householder developers may incur a charge. For further information on the historic environment and planning, and our charging schedule please refer the applicant to: https://new.devon.gov.uk/historicenvironment/development-management/.